Stage 1 & 2
Coast Wattle and Peppercress
Titles estimated: Q3 2024
Planning
100% Completion
- Plan + Permits 100%
- Engineering 100%
Civil Construction
41.1% Completion
- Site Establishment 100%
- Bulk Earthworks 95%
- Drainage Works 95%
- Sewer Works 0%
- Water & Gas Reticulation 80%
- Subgrade Placement Works 0%
- Electrical & NBN 0%
- Footpaths / Asphalt / Linemarking 0%
- Practical Completion 0%
Registration Progress
0% Completion
- Statement of Compliance 0%
- Lodge Plan of Subdivision 0%
- Titles 0%